WSDOT Continues Work On 167, Two Southbound Lanes To Close Tonight

Crews will close two lanes of southbound SR 167 between I-405 and South 180th Street. The lanes will close at 7:30 p.m. and reopen at 4:30 a.m. Wednesday.

Crews reopened State Route 167 Monday morning after a . Over the weekend, crews removed 100 feet of SR 167 pavement to dig a 25-foot-deep trench and install a 220-foot-long culvert. Crews completed the installation and, as planned, paved all but the last layer of pavement.

To add the final layer of paving, crews closed two northbound lanes of SR 167 from Monday night through early Tuesday. WSDOT will again close two lanes of SR 167 — this time in the southbound direction — from Tuesday night through early Wednesday morning.

Further Closure details:

Find out what's happening in Rentonwith free, real-time updates from Patch.

  • Tuesday, Aug. 14 – morning of Wednesday, Aug. 15 Crews will close two  lanes of southbound SR 167 between I-405 and South 180th Street. The lanes will close at 7:30 p.m. and reopen at 4:30 a.m. Wednesday.

Traffic conditions on SR 167 can be monitored on the Seattle traffic page at www.wsdot.wa.gov/Traffic/seattle.

 

Find out what's happening in Rentonwith free, real-time updates from Patch.

*Editor's Note: Information provided by WSDOT.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here